What is a key requirement of the Permit Streamlining Act regarding project application completion?

Prepare for the California Supplemental Exam with our CSE ARE Test. Use flashcards and multiple choice questions, complete with hints and explanations. Ace your exam with confidence!

The Permit Streamlining Act emphasizes the importance of timely communication between agencies and applicants during the project application process. A key requirement of the Act is that when a project application is submitted, the agency must review the application for completeness and notify the applicant within 30 calendar days. This requirement helps ensure that applicants receive prompt feedback, enabling them to correct any deficiencies or provide additional information as needed, which can facilitate a smoother and more efficient permitting process. Timely notification is crucial for maintaining project timelines and reducing unnecessary delays in development.