What should be done if concealed conditions are encountered during construction?

Prepare for the California Supplemental Exam with our CSE ARE Test. Use flashcards and multiple choice questions, complete with hints and explanations. Ace your exam with confidence!

When concealed conditions are encountered during construction, the correct course of action is to notify the Owner and Architect immediately. This approach is crucial for several reasons.

First, prompt notification allows for timely assessment of the discovered conditions. Concealed conditions can impact the project schedule, budget, and overall design, so early communication is essential to address any necessary changes or modifications appropriately.

Second, the contract typically requires that any unforeseen conditions be communicated to relevant parties so that decisions can be made that best serve the project's integrity and safety. This collaboration helps ensure that all stakeholders are informed and can contribute to determining a suitable way forward, preserving the project's objectives.

Lastly, addressing concealed conditions in a timely manner can help prevent further complications or delays, which might arise if the issues are neglected or mishandled. In construction, a proactive approach to unexpected conditions is critical for maintaining the flow of work and ensuring compliance with safety and regulatory standards.