Which construction document requires approval by the architect even if prepared by the construction manager?

Prepare for the California Supplemental Exam with our CSE ARE Test. Use flashcards and multiple choice questions, complete with hints and explanations. Ace your exam with confidence!

The correct answer encompasses the idea that all the listed documents require the architect's approval, underscoring the architect's role in the construction process.

Change orders are modifications to the original construction contract that detail changes to cost, time, or scope. Architect approval is essential because it ensures that any adjustments align with the project’s overall intent and that the budget and schedule will be adequately managed.

Applications for payment are requests made by the contractor to receive payment for work completed. The architect's approval is vital here as they must verify that the work meets the agreed-upon standards before any payments are disbursed, safeguarding the owner's investment.

Construction change directives are orders that authorize changes to the work before a change order is finalized. They allow construction to proceed without delaying the entire project while details are resolved. The architect's approval is necessary to ensure that these changes are in line with the project scope and quality standards.

By requiring architect approval for all these documents, the integrity of the project is maintained, ensuring that it remains on track, within budget, and aligned with the client's vision and requirements.